Texas-87 roadwork in Bridge City coming to a close, swing bridge rehab begins January

 

Last updated 11/27/2018 at Noon

TxDOT is about to wrap up the pavement overlay project on Texas-87 through Bridge City. Then they have plans to start their next project on the East Roundbunch Swing Bridge near Chemical Row in January.

RECORD PHOTO: Mark Dunn

For the Record

After what seems to be a long, drawn out project by some area residents, the repairs on Texas-87 through Bridge City may soon be completed.

According to Sarah Dupre, with the Texas Department of Transportation, the project could wrap up within the next two weeks.

For some the completion will come as a relief. Traffic congestion has increased and at times up to about 33,000 vehicles within a 24 hour period have been counted on Texas Avenue.

The $5.6 million project began in July 2017 and covers 5.2 miles.

To prevent an even more costly complete overhaul of the roadway, TxDOT chose to preform maintenance type of work on the project.

"What this does is so we would not have to completely reconstruct the roadway," Dupre said.

Instead, TxDOT scraped off the old pavement and made repairs to the base. They also made repairs to the curbs along with other small repairs along the roadway. Finally, they added an overlay with new pavement.

The project was met with delays during the process which was mostly due to weather conditions. The biggest delay was the heavy rain left behind by Hurricane Harvey in late August and early September in 2017.

The rain totals for 2017 were 104.3 inches which exceeds the average annual rainfall total of 60.47 inches. There was not a hurricane in 2018 to date and the rainfall totals still exceed the normal range. The rainfall to date in 2018 is 80.69 inches and the average is 54.23 inches, according to the National Weather Service in Lake Charles.

Another obstacle has been cold weather, according to Dupre.

However, even though the work may seem to be completed in Bridge City, TxDOT will then focus on another project.

Starting in January they will focus on the bridge and roadway on Roundbunch, Dupre said. This project is expected to be completed in the spring of 2019.

 

Reader Comments(0)

 
 

Our Family of Publications Includes:

County Record
Penny Record

Powered by ROAR Online Publication Software from Lions Light Corporation
© Copyright 2024

Rendered 03/27/2024 00:39